RFID + Cloud + BIM for Managing Personnel in Vertical Construction

ThingMagic has had the opportunity to design, build and run an RFID–based personnel management system on a large construction project in California. Only three months after going-live, the general contractor is blown away by the system benefits and the richness of the collected data.
Construction management and building owners used to have to wait for weeks and months to get data on how their projects have actually been staffed. The new RFID-based system provides this information in real-time during each workday. Construction site management used to deploy several security guards and supervisors for the sole purpose of monitoring the work force in different sections of the building. Using the new system, management can monitor the flow of people in and out of zones from the office trailer: if a person enters an unauthorized zone, an instant email alert is sent to the designated supervisor. Most importantly, should there ever be an emergency evacuation event on site, the system provides real-time updates on who is left in the building and where.
System Overview
We have deployed a three-tier system with a distinct sensor layer, database layer, and application layer.
describe the image
Figure 1: RFID-based Personnel Management in Vertical Construction: Major system components and system architecture.
Every worker on the construction site is issued a passive UHF-RFID-enabled ID card, which the individual wears on a lanyard around the neck. The sensor infrastructure consists of RFID-reader-enabled secure turnstiles for access to and egress from the job site; inside the building under construction we have installed Mercury6 RFID readers and antennas to systematically cover the entry areas of the building, staircase landings, man-lift landings, and the entrance areas of elevators banks. As a worker moves from one building section to another, the portal readers pick up the badge ID of the worker and associate the individual with the new space or zone. 
Raw sensor data is sent in real-time to a cloud-based database, where the data is translated into high-level events such as zone entries and exits, and then stored.
A multitude of web-enabled applications have access to the event data through a web API.
BIM Integration
The General Contractor and other stakeholders are given access to the data via a number of interfaces, including a mobile-device friendly web portal and email reports and notifications. However, the core filtering and reporting engine has been implemented as a plug-in to Tekla Structures, the comprehensive Building Information Modeling (BIM) and CAT software developed by our sister division Tekla.
The construction manager can visualize the personnel deployment on site within the 3D model. He or she has the ability to specify the time window of interest, the subcontractor, the zone, and other properties. The selected population of workers or a particular individual is presented along with a work zone selected in the model.
Benefits
Why would a general contractor or project owner deploy this system? Our RFID-based people management system provides:
  • Real-time visibility into worker location during an evacuation event
  • Instant alerts on security or safety breaches 
  • Instantaneous reports on sub-contractor staffing levels
  • Real-time updates on personnel-related compliance issues or ordinances.
Floor Detail
Figure 2: Full-time equivalent construction personnel over a period of about seven weeks by day, subcontractor, and zone of the building under construction.
Supported by RFID and cloud-computing, emerging life-cycle management solutions are enabling new levels of innovation, productivity, collaboration, and growth in the construction market and others.  Organizations that can best harness this “Big data” opportunity will hold a distinct competitive advantage.